Consent to spend
Contents |
[edit] Introduction
In construction the term 'consent to spend' is sometimes referred to as an ‘if’ contract. A letter with instructions to proceed and consent to spend allows work to proceed up to a certain value while the contract itself is still being drafted. The consent to spend letter can be a legally binding contract that pre-dates the principal contract. Once the principal contract is signed the consent to spend letter can be superseded. Consent to spend can also be captured in a letter of intent.
[edit] Consent to spend letter contents
It is good practice to capture as a minimum the following items in a consent to spend letter:
- The parties involved in the contract.
- A description of the works required to avoid ambiguity.
- A statement of the intention of the parties to enter into a formal contract.
- The price, or if the price is not known, established rates can be mentioned or the contract administrator can detail specific requirements to ensure financial control.
- The maximum expenditure limit relating to the consent to spend contract.
- The date of possession and access to site.
- The completion date if known.
- The contract administrator can refer to a short-term program.
- There might be sectional completion requirements that can be listed.
- Insurance requirements.
- Termination procedure.
- Confirmation that the contract created by the consent to spend will be terminated by the principle contract.
It is advisable to capture as much detail as possible in the letter of consent to spend. The letter can be a great advantage to the construction program, but the risk of not capturing details or covering basic clauses can result in problems.
[edit] An alternative to a consent to spend or letter of intent
An employer can use a pre-construction service agreement (PCSA) if they need the input of a contractor before the construction contract is in place. A pre-construction service agreement is a contract commonly used in two-stage tendering. Two stage tendering involves the employer tendering the project on the basis of an incomplete design. A contractor is then chosen to work with the employer based on its proposal for the pre-construction second stage of the tender.
The employer might want the contractor’s input on programming, designs and buildability prior to issuing the construction contract. In the right circumstances, a PCSA can be beneficial to both parties and bring design improvements and costs savings, and encourage a strong working relationship. A letter of intent/consent to spend is not likely to achieve the same benefits as a PCSA. A PCSA is however a formal agreement and a small-scale project might not have the budget or program to accommodate this type of formal agreement.
[edit] Conclusion
A consent to spend letter can be a good tool to expedite work on site but contract administrators need to be aware of the legal implications to avoid unnecessary risk to the project.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
ECA digital series unveils road to net-zero.
Retrofit and Decarbonisation framework N9 launched
Aligned with LHCPG social value strategy and the Gold Standard.
Competence framework for sustainability
In the built environment launched by CIC and the Edge.
Institute of Roofing members welcomed into CIOB
IoR members transition to CIOB membership based on individual expertise and qualifications.
Join the Building Safety Linkedin group to stay up-to-date and join the debate.
Government responds to the final Grenfell Inquiry report
A with a brief summary with reactions to their response.
A brief description and background to this new February law.
Everything you need to know about building conservation and the historic environment.
NFCC publishes Industry White Paper on Remediation
Calling for a coordinated approach and cross-departmental Construction Skills Strategy to manage workforce development.
'who blames whom and for what, and there are three reasons for doing that: legal , cultural and moral"
How the Home Energy Model will be different from SAP
Comparing different building energy models.
Mapping approaches for standardisation.
UK Construction contract spending up at the start of 2025
New construction orders increase by 69 percent on December.
Preparing for the future: how specifiers can lead the way
As the construction industry prepares for the updated home and building efficiency standards.
Embodied Carbon in the Built Environment
A practical guide for built environment professionals.
Updating the minimum energy efficiency standards
Background and key points to the current consultation.
Heritage building skills and live-site training.